Media reports say that now the decks have been cleared for speeding up of the widening of Jaipur-Gurgaon stretch of national highway (NH -8), which has been pending since a long time. Authorities discussed the pending issue on September 10. It is said that consensus has been reached on the issue between officials of the National Highways Authority of India (NHAI) and the Rajasthan State government.
The officials have agree to shift two high tension power lines from the Jaipur bypass (200 feet road). The issue was pending with the Jaipur discom for the past 18 months leading to delay in widening of the stretch.
The Rajasthan government also agreed to allow the concessionaire for carrying out work at Sanjay Van. Earlier, the government was demanding construction of a boundary wall from the developer, which NHAI rejected. Earlier, the government was demanding construction of a boundary wall from the developer, which NHAI rejected.