Cable Corporation of India has secured an order to lay 129 km of 230 KV EHV cable valued at Rs 140 crore from Tamil Nadu Electricity Board (TNEB) for the expansion of power supply system to minimise distribution losses and improve system reliability in the Chennai Metropolitan Area. This is the largest single order received by an Indian cable company manufacturing in India.
The turnkey project assigned to CCI over other large MNCs, includes designing of a 230 KV single core 1200 sq mm aluminium conductor XLPE insulated cable, manufactured at its state-of-the-art facility, along with detailed project engineering and supply of the accessories. The TNEB order also includes execution of the project, starting with essential spares, laying of the cable, erection of joints and terminations and final testing and commissioning. The project will be completed in 18 months.